This is the deadline timetable for our music video project. the deadline is now Monday the 16th, this what we plan to do in the two weeks we have left before the deadline.

Wednesday 4th
Lesson 9-10:30
What we want to do - This blog and continue the editing of our music.

(break)

12:25-2.40
What we want to do - Edit some previous blogs and create a new one if time.

Thursday 5th
Lesson 12:25-1:55
What we want to do - Continue blog and editing.

yr 13 lunch

1:55-2:40
What we want to do - Same as in lesson if we need to.

Monday 9th
12.20 - 1.55
what we want to do - Possibly blogging if needed.

lesson 1:55 - 3.25
what we want to do - talk about idea or our CD cover and magazine but also blogging and editing.

Tuesday 10th

Editing evening 4:10 - 8
what we want do to - we aim to finish all our editing and add any special effects etc that we might want.

Wednesday 11th

Lesson 9 - 10:30
what we want to do - do anything that is still outstanding and check that everything is finished and complete.

Monday 16th
Final lesson 1:55 - 3:25
what we want to do - double check everything do make sure we are not missing any blogs or if any lip syncing is out of time etc.